Project: Electrolux POLAND Sp. z o.o.
Placement: Oława
Period: April 2005/December 2005
Range: Washing machines production facility
Description:
Total land area: 299680 m2
Building area: 51450 m2
Effective floor space: 57230 m2 including office: 4860 m2
Building volume: 546208 m3
Paved area: ~45000 m2


Technical equipment: Boiler room 2080 kW, Compressor room 50 m3/min, cooling centre 1,5 MW, sprinkler system, medium valtage substation

Other technical infrastructure: power, water, gaz conections, vacuum system, water main, sewage, drainage, gas main, power cables, rain water tank.

MKD Company performed services as a Kajima's subcontractor.
See other projects: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8