Wrocław Water Park – building inspection
Lokalization | Wrocław |
Period of implementation | 09.2007 - 01.2008 |
Range | Building state report in the scope of: - swimming pool water treatment technology - firefighting protection - compliance with hygiene and sanitary requirements - work health and safety |
Usable area | 18 300 m2 including offices: 2 620 m2 |
Description | The Wrocław Water Park was built in the years 2004 – 2007. Many problems arose during its construction. The construction deadline was considerably exceeded. Our company was asked to compile a report regarding the state of the investment. During the inspection a number of nonconformances with construction law, health and safety and firefighting regulations were detected. Owing to this, it was possible to remove a lot of facility defects and ensure a safe use by the general public. |